CITY OF SALISBURY TO CONDUCT VALVE REPLACEMENT ON E. NORTH POINT DRIVE

news picture
June 23, 2025

Salisbury, Maryland - The City of Salisbury has announced a planned valve replacement on East North Pointe Drive as part of its ongoing improvements to the water distribution system.


The work, overseen by the Department of Waterworks Utilities Division, is scheduled for Tuesday, June 24, 2025, and will involve replacing a 12-inch valve located at the end of E. North Pointe Drive.


The project will occur in two phases. The first phase is set to begin at 7 a.m. on June 24 and is expected to conclude by approximately 1 p.m.


The second phase will resume later that evening at 9 p.m. and is slated to finish around 3 a.m. on Wednesday, June 25. These timelines are subject to change depending on unforeseen circumstances.


For the duration of the project, E. North Pointe Drive will be closed to all through traffic, including emergency vehicles. Alternate routes should be used by motorists to avoid disruptions. Advance notice has been provided to residents of Addison Court Apartments, as well as the property management team, regarding a planned interruption of water service during the work schedule.


Coordination efforts with utility locators and Central Alarm have been completed to ensure public safety and smooth execution. Additionally, the city noted that proper arrangements are in place to minimize inconvenience.


The City of Salisbury expressed its appreciation for the patience and understanding of local residents and motorists during this essential infrastructure upgrade.


For further information about the project or for specific inquiries, residents can contact the City of Salisbury Utilities Division at 410-548-3103.